HIGHLAND DISTRICT HOUSING
Description: Build a new three-story, multi-building, 770-bed residence halls, Villa del Puente, Posada San Pedro, Pueblo de la Cienega and El Portal (A/B Buildings), and Residence Life Administrative Offices located in the Highland Residential Community adjacent to Highland north of Sixth Street.
Project Number 98-7931
Phase

Project Links

Delivery Method CMR
Projected Budget $39,700,000 [learn more]
Size 280613 gross sq. ft.
145862 net sq. ft.
Construction Schedule April 2002 - February 2004
Building Number(s)
PDC Design Manager Johnson, Debra
PDC Construction Manager Dolan, Brian
Architech/Engineer AR7 Architects P C
Contractor Sundt Construction Inc
CM Sundt Construction Inc
Design Intent: