HIGHLAND AVENUE PARKING GARAGE |
|
|
|
Description: Build a 1570-space parking structure, Highland Avenue Garage, to service the northeast campus district and the Arizona Health Sciences Center (AHSC). Additional spaces are needed to meet current and projected parking demands. The parking structure is to be located on the northwest corner of the intersection of Vine and Helen Streets. |
|
Project Number |
01-8344 |
|
Phase |
|
|
Project Links
Renderings
Photo Gallery
|
|
Delivery Method |
Design/Build |
|
Projected Budget |
$18,000,000
[learn more] |
|
Size |
489324 gross sq. ft.
276255 net sq. ft.
|
|
Construction Schedule |
June 2004 - June 2005 |
|
Building Number(s) |
|
|
|
PDC Design Manager |
Mackey, Rodney
|
|
|
PDC Construction Manager |
Kraft, Chris |
|
|
Architech/Engineer |
Sundt Construction Inc / Durrant Group Inc
|
|
|
Contractor |
Sundt Construction Inc
|
|
|
CM |
Sundt Construction Inc
|
|
|
|
|
|
|
|