Lowell-Stevens Football Facility (Az Stadium, North End Zone Expansion)

Description

Construction of the new north end-zone facility at Arizona Stadium will provide upgraded premium seating and fan amenities, relocate and provide new facilities for the football program and provide new concourses cross connecting access to the east and west stadium seating sections.

Project Number 09-8902 Building Number(s) 58E
Phase Occupancy Design Manager Vos, Bill
Delivery Method CMR Const. Manager Dolan, Brian
Projected Ultimate Budget $72,300,000 Design Professional Heery International Inc
Size 183,683 gross sq. ft.
140,589 net sq. ft.
Contractor Mortenson Construction
Const. Schedule December 2011 - July 2013